Reactor Permits Pile Up Under Trump As Democrats Prepare To Take Over Nuclear Oversight

Federal regulators are clearing new nuclear reactors for construction ahead of schedule as Democrats prepare to take over oversight of the agency in January.

Simon August · · 10 min read

Federal regulators are clearing new nuclear reactors for construction ahead of schedule as Democrats prepare to take over oversight of the agency in January.

The Nuclear Regulatory Commission (NRC) issued a construction permit Nov. 9 for a four-reactor plant at a Dow chemical site in Calhoun County, Texas, the agency announced. Democrats decisively won control of Congress in the Nov. 3 midterm elections and will chair the committees with power over the NRC.

The permit allows Long Mott Energy to build the plant but “does not authorize operation,” which requires a separate NRC license, the agency said.

Dow has not committed to building it.

“Receipt of the construction permit does not represent a final decision by Dow to proceed with construction of the proposed facility,” the chemical company said in a Nov. 9 statement.

“We delivered on the 18-month schedule, proving we can do rigorous safety reviews on predictable timelines that move advanced nuclear technology from design to construction,” NRC Chairman Ho K. Nieh said in the release.

X-energy, Dow and the office of Democratic New Jersey Rep. Frank Pallone, the top Democrat on the House Energy and Commerce Committee, did not respond to the Daily Caller News Foundation’s requests for comment. Pallone is widely expected to chair the committee when Democrats assume control of Congress in January.

ClearPath, a conservative clean energy group, said support for nuclear power crosses party lines.

“Both Republicans and Democrats recognize the value of nuclear energy,” Niko McMurray, the group’s managing director of international and nuclear policy, said in a statement to the DCNF.

The group said the House “recently passed six nuclear energy bills with overwhelming bipartisan support,” and some of them are in the permitting reform bill dubbed the Bipartisan American Affordability and Jobs Act (BAAJA).

“Building on the work of the last several Congresses and Administrations, the next Congress can continue to support efficient, predictable licensing that gives companies the certainty to invest in new technologies. That certainty is critical to adding reliable power to the grid and keeping consumer costs down,” McMurray said.

That makes Long Mott the third advanced reactor project the NRC has cleared for construction in 2026, the agency said, and the first high-temperature, gas-cooled design to get a permit in almost six decades. Staff finished the safety review in October, a month early.

NRC Senior Public Affairs Officer Maureen Conley said in a statement to the DCNF that staff wrapped up the Long Mott review early by using a core team of technical experts and by working closely with the applicant, Long Mott Energy.

“These processes are being applied to advanced reactor applications under review and will continue to be applied to future applications,” Conley said.

Asked what staffing or funding the agency needs from Congress next year, Conley said the NRC has “formulated our budget for fiscal year 2027 with a focus on planning for the agency’s expected workload.” She did not give staffing or funding figures.

The plant would use four X-energy Xe-100 reactors to supply steam to Dow’s Seadrift Operations site. “Excess electricity will be exported to the grid,” the NRC said.

The company said it could break ground later this decade and bring the plant online early in the next one if its board approves the project. X-energy said Dow is expected to weigh a preliminary decision on investing in the project in 2027.

“As we move forward, we will continue to evaluate the project through the lens of competitiveness, execution readiness, and capital affordability before any decision regarding construction is made,” Dow business vice president Edward Stones said in the statement.

The first of the year’s three advanced reactor approvals came March 4, when the NRC cleared TerraPower’s Kemmerer Unit 1 in Wyoming for construction. The agency said it was its first approval to build a commercial reactor in nearly a decade.

The second came in September, when the agency approved the Tennessee Valley Authority’s Clinch River project near Oak Ridge, Tennessee. The NRC said that its review took 14 months, and GE Vernova said that no other U.S. project had won a permit to build its BWRX-300, a small modular reactor design.

“Four months ahead of schedule is what the new NRC looks like,” Nieh said at the time.

Nieh said Nov. 3 that the faster pace is now the norm. “Construction permits are being issued ahead of schedule,” he said in remarks to the Institute of Nuclear Power Operations’ CEO conference.

“The NRC cannot backslide from this point. We must adapt on our own as the regulatory landscape changes. It should not take a president’s order or an act of Congress to improve the NRC in the future,” Nieh said.

In 2024, lawmakers passed the ADVANCE Act, a bipartisan law meant to speed advanced reactor licensing. A May 2025 executive order from President Donald Trump then told the NRC to reform its licensing and set firm deadlines for decisions on new reactors. Both moves came before Long Mott.

J. Clay Sell, the CEO of X-energy, gave the agency and Congress credit on Nov. 9. “Getting the construction permit earlier than expected is reflective of the thorough and efficient work of the NRC, the reforms that have been put in place by the Congress over the last six years, and the phenomenal work of the X-energy and Dow teams,” Sell said in a company statement.

On Nov. 12, the commission adopted a rule that routes fewer licensing actions to the Advisory Committee on Reactor Safeguards, an outside panel of experts that reviews reactor safety. That was three days after the Long Mott permit.

“This reform focuses that expertise where it matters most — on the novel and safety-significant issues that require the Committee’s expertise — while helping the NRC make timely, well-supported licensing decisions,” Nieh said in a release.

The Senate passed the BAAJA, a broad permitting bill, 62-33 on Nov. 19, the Senate Environment and Public Works Committee said. The House would still have to act.

ClearPath Action CEO Jeremy Harrell urged the House to pass it in a statement to the DCNF. “After years of debate, the Senate has finally passed a bipartisan permitting bill that will let America build,” Harrell said.

Democratic Oregon Sen. Jeff Merkley stated that he wants to lead the Senate Environment and Public Works Committee, which oversees the NRC, The Hill reported.

“I am excited to announce the plan to seek the chairmanship of EPW in the next Congress,” Merkley said, according to The Hill.

Democratic Rhode Island Sen. Sheldon Whitehouse, the committee’s top Democrat, is expected to lead the Judiciary Committee instead, the outlet reported.

Pallone said Nov. 4 that he will ask House Democrats to back him as chairman of the Energy and Commerce Committee. Lowering costs, health care, consumer and environmental protection, clean energy and Big Tech were the priorities his statement listed, and nuclear power was not among them.

Pallone tied his support for nuclear bills to transparency at a September markup.

“I want to once again state that my support for nuclear energy legislation is contingent upon the Nuclear Regulatory Commission and the Department of Energy having sufficient transparency into their safety rules and regulations, so the American public can be sure that our nation’s nuclear industry is safe,” he said at a Sept. 2 committee markup.

He said he would back all six if amendments to two of them were adopted.

“If the amendments for those bills are adopted, I will support all six nuclear bills on today’s markup,” Pallone said.

Allison Macfarlane, who chaired the NRC under former President Barack Obama, said in a statement to the DCNF that the commission is “no longer an independent regulator and is marching to President Trump’s tune.”

“I don’t really know what’s happening at the NRC now,” Macfarlane said. In the past, she said, the pace of licensing “largely depended on the applicant.”

“Japan did not have an independent regulator before the Fukushima accident, and we saw the consequences of that,” Macfarlane said.

She said Congress should focus next year on “the independence of the agency and its ability to fulfill its mission to protect public health, environmental health, and security.”

Jacopo Buongiorno, a nuclear science and engineering professor at MIT, said in a statement to the DCNF that construction permits take “less time and a lower depth of analysis” than operating license reviews. He said those reviews will “slow things down,” especially for unfamiliar technologies.

He said “licensing is not the bottleneck at the moment” and that getting nuclear-grade parts and fuel delivered, and how well construction projects are run, will decide how fast reactors are deployed.

Adam Stein, director of nuclear energy innovation at the Breakthrough Institute, said in a Nov. 9 statement that Long Mott shows the NRC “can execute rigorous safety and environmental evaluations for multiple new reactor designs on predictable and commercially viable timelines.”

“These are important steps toward a regulatory framework that reflects the characteristics of advanced reactors,” Stein said.

“Making this approach routine will be essential to deploying advanced nuclear energy at scale for both electricity and industrial heat,” Stein said.

The Nuclear Innovation Alliance, a nuclear policy group, has backed many of the NRC’s proposed changes while asking for more openness.

“It is essential that NRC provide much greater transparency, for example, by publishing what the staff sends to the Commission, releasing the Commissioner voting records, and explaining the role of NRC’s rulemaking steering committee,” the group said in a Sept. 3 statement.

It also asked for guardrails.

“We believe many of the proposed rules would enable more effective and efficient licensing, but NRC must put guardrails in place to ensure the continued achievement of adequate protection of public health and the environment,” the group’s statement added.

The nuclear policy group said it is “continuing to advocate for an NRC that maintains public trust and its international reputation.”

Judi Greenwald, the group’s president and CEO, said in a statement to the DCNF that it is “hard to predict” whether transparency could be what wins bipartisan backing for nuclear legislation, but that recent actions “make us think this is likely.” She pointed to a Sept. 18 letter in which the top Democrats on the House and Senate appropriations subcommittees that fund the NRC asked the agency for more transparency.

“Durable progress depends on having enough people, resources and public trust. Transparency and independence are what maintain public trust,” Greenwald said.

In his Nov. 3 remarks, Nieh said what worries him most. “In my view, the most serious risk to these regulatory reforms is a significant operational event that would undermine the trust and confidence the American people have in nuclear power,” he said.

The NRC is also reviewing Palisades SMR’s phased application for a construction permit. The first part, which also seeks approval for early site work, covers two Holtec SMR-300 reactors in Covert, Michigan, according to the agency’s project page.

The company filed the second, main part of the application Sept. 30, and NRC staff is “currently undertaking its acceptance review,” the agency said in a Nov. 10 Federal Register notice.

The NRC has set March 31, 2027, as its target for the final safety evaluation and final environmental impact statement on the first part of the application.

All content created by the Daily Caller News Foundation, an independent and nonpartisan newswire service, is available without charge to any legitimate news publisher that can provide a large audience. All republished articles must include our logo, our reporter’s byline and their DCNF affiliation. For any questions about our guidelines or partnering with us, please contact licensing@dailycallernewsfoundation.org.