Consumer Watchdogs From Ohio To Illinois Want Grid Auction Delayed Over Data Center Costs
Consumer advocates in seven states want a regional grid operator to delay its December auction, saying it could stick households with the bill for data centers.


Consumer advocates in seven states want a regional grid operator to delay its December auction, saying it could stick households with the bill for data centers.
Eight consumer offices, two of them from Illinois, asked the board of PJM Interconnection on Wednesday to seek federal approval to postpone the Dec. 9-15 auction, according to their letter. PJM’s independent market monitor warned Nov. 12 that the auction could cost all customers another $5 billion to $10 billion tied to data centers.
“It is common sense that ordinary households should not be paying billions in added costs for data centers, yet that is what is highly likely to happen if PJM proceeds with its December auction that includes a massive amount of forecasted data center electric demand growth,” Maryland People’s Counsel David Lapp said in a press release.
“Ohio families should not be forced to pay higher electricity bills to subsidize the enormous power demands of data centers,” the Office of the Ohio Consumers’ Counsel told the Daily Caller News Foundation in a statement.
“The precise impact on Ohio households is not yet known and will depend on the auction results and how costs are allocated,” the office added. If PJM’s board declines, the office is “evaluating potential action” before the Federal Energy Regulatory Commission (FERC).
Asked about the auction’s effect on monthly bills for typical Maryland households, Lapp told the DCNF in a statement that running it on schedule would not raise bills above earlier years, since it would clear at the same price cap. But it would “maintain excessive costs in excess of $10/month, and possibly much higher, for customers due to data centers,” he added. His office is also “considering options for action at FERC,” he said.