Lansing Board Approves Data Center Ban Amid Challenge
Lansing, New York’s Town Board voted 3–2 to ban data centers and cryptocurrency mines, but the measure’s fate remains uncertain after TeraWulf submitted a landowner protest that could require four votes to pass. Town officials are determining whether the petition meets state law’s requirements; if it does, the ban would fail, while a rejection would allow the law to proceed. The dispute centers on TeraWulf’s proposed large computing campus at the former Milliken power plant on Cayuga Lake, with project estimates ranging from about 300 megawatts to as much as 400 megawatts of capacity. Opponents cite potential effects on electricity costs, water use, noise, pollution, the lake and the tourism economy, while TeraWulf has pointed to possible jobs and tax revenue, and some residents say individual projects should be reviewed rather than barred outright.