Puerto Rico Court Voids LUMA Grid Extension
Puerto Rico’s Supreme Court ruled 5-4 to void the 2022 extension of LUMA Energy’s agreement to operate the island’s power grid, finding it lacked required approval from the public-private partnership agency. The original contract’s transition terms remain in force, requiring LUMA to help transfer operations to a successor within a year; Gov. Jenniffer González Colón says her administration will seek a new operator and blames LUMA for outages and high electricity costs. The ruling comes amid years of service complaints and persistent power problems, while a federal financial oversight board has warned that ending the agreement without a clear successor plan creates uncertainty about continuity of service. The dispute also raises questions about the costs of LUMA’s exit and the implications for Puerto Rico’s creditors and ratepayers.