Alabama Tightens Data Center Contract Reviews As Critic Questions Customer Protections
Alabama regulators tightened their review of the financial protections in Alabama Power’s data center contracts under rules taking effect on Monday.
Simon August · Nov 23, 2026 · 4 min read

Alabama regulators tightened their review of the financial protections in Alabama Power’s data center contracts under rules taking effect on Monday.
Alabama Power filed the revised rate schedule on Nov. 5 after an order from the Alabama Public Service Commission on Nov. 3, according to the filing. The schedule lists Monday as its effective date.
The length of the deal and its minimum payments will be reviewed alongside upfront money and collateral, according to the filing. The schedule does not require every customer to agree to the same minimum contract length or payment percentage.
Its large-load agreements already require those financial commitments, Alabama Power said in a statement to the Daily Caller News Foundation.
“Alabama Power requires large-load customers, like data centers, to pay the full cost to serve their energy needs, so costs are not shifted to existing customers. The Alabama Legislature reinforced our position by writing that same standard into state law,” the statement added. “Additionally, each large-load agreement includes minimum bills and term lengths, upfront payments, and security and collateral, so if a project scales back or leaves, families and small businesses are protected.”
Alabama should set minimum financial protections in the public schedule, Daniel Tait, executive director of Energy Alabama, said in a statement to the DCNF. His group participated in the proceeding, according to the commission’s docket.
“The November order adds collateral and minimum payments to the list of things the Commission will consider but does not actually set what those minimums should be, nor will it make those terms public,” he said.
Other customers could face costs while Alabama Power waits to recover its investment from a data center, Ari Peskoe, director of Harvard Law School’s Electricity Law Initiative, said in a statement to the DCNF. He questioned how the utility would decide which infrastructure costs to assign to a data center.
“If it takes decades to recover costs, then other ratepayers will make up for the shortfall,” he said. “Perhaps over the long run, ratepayers ultimately benefit, but in the short term they may lose.”