Big Electricity Users Say Grid Operator Handed Local Utilities $3.8 Billion In Power Lines Without Bids
Industrial power users want federal regulators to force a regional grid operator to let competitors bid on four new power lines.
Simon August · Nov 27, 2026 · 5 min read

Industrial power users want federal regulators to force a regional grid operator to let competitors bid on four new power lines.
Southwest Power Pool (SPP) skipped competitive bidding on about $3.8 billion in transmission projects by wrongly labeling them short-term reliability fixes, the Electricity Transmission Competition Coalition and the Industrial Energy Consumers of America alleged in an Oct. 28 complaint to the Federal Energy Regulatory Commission (FERC). SPP’s answer is now due Dec. 17 after FERC pushed back the deadline, according to a Nov. 16 notice.
“By using the need date that cannot be met to preclude competition, SPP is losing the benefit of competition without a legitimate reason,” the coalition wrote in comments to SPP that the complaint quotes.
“Rto’s [regional transmission organizations] do not have any accountability to ratepayers … and incumbents have too much influence over the RTOs,” Paul Cicio, president and CEO of the Industrial Energy Consumers of America, told the Daily Caller News Foundation in a statement.
The coalition speaks for companies that consume electricity, but its members also include think tanks and “non-incumbent transmission developers,” according to the complaint.
Transmission rates are “the fastest growing part of consumer electricity bills,” the complaint states.
SPP’s rules let it hand a project straight to the local utility only if the project is “required to be in service within three years or less to address an identified reliability violation,” the complaint states. None of the four lines is scheduled to enter service before May 2029, according to the complaint.
One is a 239-mile line running from the Texas Panhandle into southeastern New Mexico. SPP said the line was needed by June 1, 2026, its December 2025 project report shows. That line is not scheduled to enter service before Nov. 18, 2030, according to the complaint.
The projects “have already been assigned and the Designated Transmission Owners are in the process of developing and/or constructing them,” SPP wrote in a Nov. 6 motion to FERC.