Here Are The Governors Who Want To Put The Freeze On New Data Centers
Governors who promised to halt new data centers over rising power bills will find that most of their tools stop at state agencies.
Simon August · Nov 29, 2026 · 8 min read

Governors who promised to halt new data centers over rising power bills will find that most of their tools stop at state agencies.
Governors or governors-elect in nine states have promised or ordered pauses on new data centers, according to Cleanview, a data center and power project tracker. The nine states hold 158.6 gigawatts, or 41 percent, of planned U.S. data center capacity, the firm found in a Nov. 4 analysis.
Texas alone accounts for 88.4 of those gigawatts, and outgoing Republican Gov. Greg Abbott — who lost his bid for a fourth term to Democratic Gov.-elect Gina Hinojosa on Nov. 3 — froze state permits for data centers there from September until mid-November, CBS Austin reported.
“Most candidates said a moratorium would last until the new rules are written. That means the ultimate impact of Tuesday’s results won’t be known until next year when state legislatures meet,” Cleanview’s Michael Thomas wrote in the analysis after the Nov. 3 elections.
The 56.7 gigawatts already under construction across the country face less risk, because the pauses target new building. Projects in those states that have yet to break ground will likely see delays, the Cleanview analysis said.
Abbott had state regulators audit each data center that wanted to hook into the state’s main grid. On Sept. 21, he told the Texas Commission on Environmental Quality to stop issuing data center permits until that audit was done, his office said.
“Data centers must pay their own way, protect our grid and water, and complete the ERCOT [Electric Reliability Council of Texas] and TWDB [Texas Water Development Board] audits. Until they do, TCEQ [Texas Commission on Environmental Quality] will issue no permits sought by data center projects,” Abbott said in the announcement.
Abbott’s office told the commission Nov. 13 that it could resume data center permits and that “ERCOT has completed the community impact review,” CBS Austin reported. The Electric Reliability Council of Texas runs most of the state’s grid. Hinojosa, who unseated Abbott on Nov. 3, takes office Jan. 19.
“When I am governor I will issue a moratorium — a ban — on all data center approvals until laws can be passed by the Legislature to protect Texans,” Hinojosa said in an Oct. 22 video, the Texas Tribune reported.